Hi all,

I have updated my NW T-Way Audit and complience document and placed it here

http://homepages.ihug.com.au/~mpgoard/files/NW_Tway%20cycleway%20pt%20x1.doc

for retrieval.  Warning the document is large, 11 MBytes.  This can be added to, and corrected if necessary, and used for CAMWest submissions.

I am hoping to get along the T-way further north this weekend.
give me a call, or email, if you wish to join me to survey and document, and photgraph.

Regards
 
Michael Goard
mpgoard at ihug.com.au
Phone: +61 415 191 405

  ----- Original Message ----- 
  From: jonhol2 at netscape.net 
  To: camwest-discuss at nicku.org 
  Cc: aunwin at bicyclensw.org.au 
  Sent: Tuesday, April 10, 2007 5:09 PM
  Subject: [CAMWEST-discuss] Parramatta T-Way & BNSW


  Hello everyone,
                     I spoke with Alex Unwin today about the involvement of BNSW in the Parramatta T-Way problems. Alex has suggested that CamWest put together a submission to BNSW regarding the issue and he will take that to the Minister which will hopefully also raise the issue with the RTA. His sugestion was also that I approach him in this instance as a member of CamWest in the first instance & stating that I am also a Board Memebr of BNSW.

  Alex suggested that we condense our current discussion emails on this issue and forward them to him, together with the fact that we are trying to meet with Parramatta City Council Traffic Commitee re same.

  He also suggested some contact with Blacktown City Council re this issue as well. To that end, is anyone aware of problems or incomplete areas of the track beyond Parramatta's jurisdiction that we can document and raise with the Minister's office & RTA?

  After my ride of a small section of the cycleway, I was amazed at the lack of maintenace & the state of the track already. I was also surprised at the state of the start of  M7 section & I am led to believe that there has been at least one significant mud slide further along that path. Can some one confirm this please, along with the current state of the M7 path?

  Therefore, could you please forward any additional problems or issues that you may be aware of regarding this costly, yet currently mostly useless piece of infrastructure as soon as possible through the discussion board? I will compile a reply to Alex as soon as I have a sufficient amount of information, possibly by this time next week. I will forward a copy to the discussion before forwarding it to Alex.

  Thanks

  John Holstein

  "if we don't change direction, we will end up where we are headed"

------------------------------------------------------------------------------
  Check Out the new free AIM(R) Mail -- 2 GB of storage and industry-leading spam and email virus protection.



------------------------------------------------------------------------------


  _______________________________________________
  CAMWEST-discuss mailing list
  CAMWEST-discuss at nicku.org
  http://nicku.org/mailman/listinfo/camwest-discuss
  CAMWEST web site: http://camwest.pps.com.au/
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://nicku.org/pipermail/camwest-discuss/attachments/20070414/14eb50b4/attachment-0001.html>


More information about the CAMWEST-discuss mailing list